TATA Steel to reduce energy costs by GBP 68000 a year

TATA Steel expects to reduce energy costs by GBP 68,000 a year following the installation of five industrial drives on pumping applications at its Rotherham plant. The Yorkshire steel plant produces speciality steels for customers in the aerospace, oil and gas, power generation and the manufacture of industrial bearings.

ABB Drives Alliance member Halcyon Drives supplied, installed and commissioned three, 90 kW and two 75 kW ABB industrial drives to control critical pumping applications at the plant.

Rated at IP55 to stop the ingress of dust and moisture, the drives feature in built intelligent pump function, multi pump control. This can ensure that an optimum number of pumps is running to meet the process demand and brings a backup pump online in the event of a pump failure.

As part of its energy saving plan, TATA Steel identified its flume flush pumps and filter feed pumps as prime candidates for energy efficiency improvements. During production, hot steel billets are cut by a gas cutter, generating scrap material that flakes off the billet.

The three 90 kW flume flush pumps are used to flush water across the billet to carry this scrap away. Whilst in production, two flume flush pumps run continuously. This scrap is filtered out of the water, which is then returned to the process via a holding tank, known as a clear well, by two duty 75 kW filter feed pumps.

All these pumps were originally driven by motors running direct on line, with no form of speed control and with only simple logic control to determine how many pumps needed to operate. Another drawback was that because the flushing water was not controlled by demand, much of it was sprayed beyond the cutting area, resulting in a lot of wastage.

TATA Steel's team of engineers carried out their own investigation, which indicated that controlling the pumps by variable speed drives would provide significant savings. In particular, the investigation on the filter feed pumps showed that only one pump would be needed to meet the demands of the re circulating water system. One of these pump sets will be removed and used as a spare.

A Halcyon Drives hire drive was installed on the pump applications to confirm the potential savings. On the filter feed pumps, the current was logged for a full day on one pump under the existing flow control system, in which two pumps are run with a flow control valve to maintain the clear well level at 60%.

The results showed that with two pumps running, annual energy used was over 355,000 kWh, at a cost of over GBP 46,000 per annum. A variable speed drive was then installed on one of the pumps and this was set up to maintain the clear well level using a level transducer. The flow control valve was forced fully open so that it wouldn't restrict flow.

Engineers found that a single pump under variable speed drive control was able to maintain the clear well level. Energy use fell to just over 131,000 kWh per annum at a cost of GBP 8,500. Savings on this application were calculated at GBP 37,600 per annum.

For the flume flush pumps, a similar exercise showed that energy use would fall from 565,000 kWh to 323,000 kWh, with costs falling from GBP 73,500 to GBP 42,000, a saving of over GBP 31,000.

ABB said that total savings were calculated to be GBP 68,000 a year once the drives were fitted permanently. Including all associated costs, this equates to an expected return on investment of around 13 months.

Mr Ben Holroyde, an engineer from the casting department and a member of the team responsible for implementing energy saving schemes, said that part of the decision making process when choosing energy saving projects involves looking at their commercial viability, as well as at the actual energy saved.

He added that "We look for schemes that will pay back within two years so for a project to pay back in such a short time was phenomenal. We have a good working relationship with Halcyon and we were very pleased with the project, with the permanent drive installation fitted in six weeks. As well as the energy savings we will make, noise has also been reduced in the area, giving better working conditions for maintenance staff."

Source - Process Engineering